RHINTE00.
Short text
Transfer Organizational
Assignment (PA -> PD)
Description
This report reads the
infotype records of the Organizational Assignment infotype (0001) created in PA.
The system then checks
whether all or some of these records exist in PD.
If all these records
exist in PD, that is for the entire validity period of the PA record, a log is
output. The log indicates that no changes are required in PD and no batch input
session is created.
If changes are required,
the system creates the following records in PD according to the Create Object(s) and Create Relationship(s) parameters.
Objects (infotype 1000):
- Work center
- Job
- Organizational unit
- Position
- Person and position (or work center)
- Position and job
- Position and organizational unit
- Cost center and organizational unit or position (depending on the Relate Cost Center with parameter).
The system only creates
objects and relationships with objects that are used in HR Master Data. The
objects are created in the validity period they have in the relevant check
tables for master data.
If the validity periods
of the PA and PD records border each other or overlap, a continuous record is
created in PD or the existing record is extended (thereby avoiding splits in
the validity period).
- Example of bordering records: The following example illustrates how a PA record and a PD record that border each other are merged into one record in PD after report RHINTE00 has been run.
Record in PA:
|<---PA RECORD--->|
Record in PD:
|<--PD-RECORD-->|
Record in PD after RHINTE00 has been run:
|<---------PD RECORD----------->|
|<---PA RECORD--->|
Record in PD:
|<--PD-RECORD-->|
Record in PD after RHINTE00 has been run:
|<---------PD RECORD----------->|
- Example of overlapping records:The following example illustrates how a PA record and a PD record that overlap each other are merged into one record in PD after report RHINTE00 has been run.
|<-----------PA RECORD--------->|
Record in PD:
|<----PD RECORD----->|
Record in PD after RHINTE00 has been run:
|<---------PD RECORD----------->|
Record in PD:
|<----PD RECORD----->|
Record in PD after RHINTE00 has been run:
|<---------PD RECORD----------->|
The settings of the
switches PLOGI TEXTO, PLOGI TEXTC, and PLOGI TEXTS dictate which texts are
copied to the ObjectAbbreviation (SHORT/Length=12) field of the PD object for organizational
units, jobs, and positions.
You can find these
switches in the Implementation Guide (IMG) for Personnel Management under Organizational
Management -> Integration -> Integration with Personnel Administration -> Set Up Integration with Personnel Administration.
If these switches are
activated, (value ='X'), the text of the PA object is transferred (and
if necessary reduced to 12 characters) to the Object Abbreviation field of the PD object when report RHINTE00 is
run.
If these switches are
not activated (value = ' '), the system transfers the object ID of the PD
object to the ID field when report
RHINTE00 is run.
Example:
The object ID of the PD
object is '00001000'.
Text for organizational
unit in PA:
Department 1
Department 1
Text in PD after
RHINTE00, if PLOGI TEXTO='X':
Department 1
Department 1
Text in PD after
RHINTE00, if PLOGI TEXTO=' ':
00001000
00001000
In both cases, the text
of the PA object is transferred to the Object Name (STEXT) field of the PD object.
Employees who have
already left the company at the time the report is run, obtain a position
relationship in HR-PD only up to the leaving date.
If the leaving is to be
transferred to HR-PD for employees who have already been transferred, you must
select the parameter Transfer Leavings Only. In this case, only the relationships that still exist in HR-PD
of employees who have already left are delimited. No records are created.
Note:
This report does not allow you to transfer an employee's leaving and subsequent reentry simultaneously. However, you can do this by running the program twice (once for the leaving, and once for the reentry).
This report does not allow you to transfer an employee's leaving and subsequent reentry simultaneously. However, you can do this by running the program twice (once for the leaving, and once for the reentry).
After this report has
been run, a batch input session (BTCI) must be processed (exception: if it is a
test run or no changes are required in PD).
You can start the batch
input session from the menu under System -> Services -> Batch Input -> Process. The session contains the name of the user who started report
RHINTE00.
The report uses the
standard relationships listed in Customizing under Maintain Relationships to create relationships between said objects.
Selection
You make the entries
according to standard selection for file PAnnnn. You must enter a start and end
date for the time interval to be processed (default values: 01/01/1800 to
12/31/9999; ensures complete consistency between PA and PD).
Report-Specific Settings
The parameters of this
report allow you to define the following:
- The target plan version for the relevant objects and relationships (the standard target plan version is the integration plan version set up in Customizing under Set Active Plan Version).
- Whether records are to be created in PD (transfer of organizational assignment) or delimited (transfer of employees' leaving). Records are created in the standard system.
- Status to be used for relationships and objects (active or planned; only active for integration plan version).
- Percentage to be used in the relationship (standard is 100%)
- Whether objects and relationships are to be created. In the standard system, this option is selected = yes.
- Object type with which relationships with cost centers are created (standard is O = organizational unit).
- Whether old holder relationships are to be delimited (if can be decided technically).
- If and under which name a batch input session is to be created.
For more information,
see the documentation for the individual parameters:
Create Object(s)
This parameter enables you
to specify whether integration objects (positions, jobs, and organizational
units) are to be created.
Only objects that are used in HR Master Data are created.
Only objects that are used in HR Master Data are created.
Create Relationship(s)
This parameter enables
you to specify which of the following relationships are to be created:
- Position - person
- Position - job
- Position - organizational unit
- Position or organizational unit - cost center
Only relationships
between objects that are used in HR Master Data are created.
Delimit Old Holder Relationships
This parameter provides
you with the following options:
- None (Presetting) : If you select this option, the system response is the same as before the functional enhancement, see SAP Note 637221. No holder relationships (infotype 1001, subtype A008/B008) for this person are delimited in PD.
Exception:
If the Customizing setting of the time constraint for IT 1001/B008 < = '2', a person can only occupy one position at a time, thereby implicit delimitations occur. In this case, you must check all the holder relationships of this person and, if necessary, delimit them manually.
If the Customizing setting of the time constraint for IT 1001/B008 < = '2', a person can only occupy one position at a time, thereby implicit delimitations occur. In this case, you must check all the holder relationships of this person and, if necessary, delimit them manually.
SAP recommends you use this option, which is
selected as standard. For an explanation, see SAP Note 554412.
- Only positions from IT 0001
If you select this option, the report delimits
previous, individual holder relationships in PD if the following conditions
apply:
- A previous record with a different position has been found for each of the infotype 0001 records selected.
- Corresponding holder relationships with a validity identical to that of the transfer date have been found in infotype 0001 for these previous records.
In this case, the corresponding records are
delimited as of the transfer date.
Exception:
If the corresponding holder relationship starts on the same date as the transfer in infotype 0001, this relationship is only delimited (or, in this case, deleted) if the staffing percentage of a previous record in infotype 1001 for the same position has not changed. If it has changed, it is assumed that the relationship was created intentionally in PD and it is therefore not delimited.
If the corresponding holder relationship starts on the same date as the transfer in infotype 0001, this relationship is only delimited (or, in this case, deleted) if the staffing percentage of a previous record in infotype 1001 for the same position has not changed. If it has changed, it is assumed that the relationship was created intentionally in PD and it is therefore not delimited.
Caution:
In the case of multiple assignments (one person occupies several positions), a maximum of one holder relationship is delimited in PD for each selected infotype 0001 record. The relationship that is saved in infotype 0001 is delimited.
In the case of multiple assignments (one person occupies several positions), a maximum of one holder relationship is delimited in PD for each selected infotype 0001 record. The relationship that is saved in infotype 0001 is delimited.
Example:
The following example illustrates what RHINTE00
does if the Only Positions from IT 0001 option is selected.
The following abbreviations are used: S =
position, I = start and end selection of infotypes.
Before RHINTE00 has been run:
Selection period:
|
I------------------------
|
Infotype 0001
|
I---S1-----I-S2--I--S2-I---S3------
|
Infotype 1001/AB008
|
I---S1----------------------------------
|
"
|
I---S4--I-------S4------------I--S4--
|
After RHINTE00 has
been run:
|
|
Infotype 1001/AB008
|
I---S1-----I
|
"
|
I-S2---------I
|
"
|
I---S3--------
|
"
|
I---S4--I-------S4------------I--S4--
|
- All
If you select this option, all holder
relationships in PD that intersect the selected records are delimited as of the
start date of the first selected infotype (or deleted if the holder
relationship starts later than the first selected infotype 0001 record).
Caution:
SAP recommends you use this option only if you can ensure that persons in the selection period cannot occupy several positions at the same time meaning that no multiple assignments could exist.
If multiple assignments do exist, this may result in required holder relationships being deleted unintentionally if, contrary to expectation, multiple assignments are intended for some persons.
SAP recommends you use this option only if you can ensure that persons in the selection period cannot occupy several positions at the same time meaning that no multiple assignments could exist.
If multiple assignments do exist, this may result in required holder relationships being deleted unintentionally if, contrary to expectation, multiple assignments are intended for some persons.
Example:
The following example illustrates what RHINTE00
does if the All option is selected.
The following abbreviations are used: S =
position, I = start and end selection of infotypes.
Before RHINTE00 has been run:
Selection period:
|
I------------------------
|
Infotype 0001
|
I---S1-----I-S2--I--S2-I---S3------
|
Infotype 1001/AB008
|
I---S1----------------------------------
|
"
|
I---S4--I-------S4------------I--S4--
|
After RHINTE00 has
been run:
|
|
Infotype 1001/AB008
|
I---S1-----I
|
"
|
I-S2---------I
|
"
|
I---S3--------
|
"
|
I---S4--I--I
|
Note:
Irrespective of the
option you select here, all the relevant data for infotype 0001 records found
in the selection period are created again in PD according to the defined time
constraint logic.
Records listed in the
list output of the report under Delimited or Deleted Relationships, can also appear under the records to be added.
In this way, a technical delimitation is described.
Provided they are
available in the release you use, you can then run run report RHINTECHECK or
RHINTE20 to find any remaining inconsistencies.
For more details and
information about the technical background, see SAP Note 637221.
Session Name
This parameter enables
you to enter a name for the batch input session that is created by this report.
Test
This parameter enables
you to specify whether a batch input session is to be created. If you select
this parameter, a test run is executed without creating a batch input session.
Output
The report outputs a
batch input session or a list of objects found for the session. It also outputs
a list of personnel numbers for which no relationship with a position exists.